Project Highlights
Project Team
Owner: City of Charlottesville
Owner’s Representative: PDG
Architect: Rodriquez, Ripley, Maddux & Motley
Project Delivery System
Conventional design/bid/build. PDG provided Owner Representative Services including schedule analysis, contract administration, and construction management from pre-construction through project closeout.
Schedule Performance
Completed on time.
Cost Performance
$7,100,000