PDG provided Owner Representative/CM services to the City for this multi-phased renovation project. Despite the extremely tight Phase 1 schedule constraints, we helped coordinate the moving of every non-fixed piece of furniture and equipment in the building over a long weekend in order to facilitate abatement activities. PDG also provided CM services for the similarly constrained Phase 2 project, which includes replacement of MEP systems, also interior renovations and finishes during a 10-week construction window.
Project Highlights
Project Team
Owner: City of Charlottesville
Owner’s Representative: PDG
Architect: Rodriguez, Ripley, Maddux & Motley
Contractor: Martin Horn, Inc.
Project Delivery System
Conventional design/bid/build. PDG provided Owner’s Representative Services including value engineering, contract administration and construction management from bidding phase through project closeout. Phase I was completed in 2003 and Phase II was completed in the Summer of 2004.
Construction Type
Renovation:
- Abatement of lead paint and asbestos containing materials throughout the facility.
- Selected replacement of doors, glazing and fixed/movable partitions.
- Replacement of MEP systems, including new building automation systems.
- Interior painting and new finishes (ceilings, VCT, carpet)
Schedule Performance
Completed on schedule.
Cost Performance
$1,500,000 – on budget.